PENTAGON’S “LEAD BALLOON” SOON TO LIGHT UP IOWA SKIES

It took the Army years to create this disaste scenario, yet it's resolution is being done under "emergency" settings.
The Pentagon Had Months. Middletown Got an Emergency.
In Iowa, the Army is preparing to destroy nearly five tons of unstable explosives. In Kuwait, six soldiers died at a command post whose protection had been questioned. Both cases demand an accounting of who knew about the risk, who had the authority to act, and what they did with the time they had.
By Francis J. Bell | November 24, 2026
The Army says families near the Iowa Army Ammunition Plant can get hotel rooms through Friday. It has told parents in potentially affected areas to keep their children inside and, once the air clears, wet-clean outdoor toys and play equipment. At about 9 a.m. Central on Wednesday, weather permitting, the Army plans to detonate nearly five tons of deteriorated lead azide at the plant in Middletown. The recommended relocation zone extends in a five-mile cone southwest of the installation. The move is a precaution against a plume that could carry toxic lead dust off Army property. [1]
Those are instructions for the week of the blast. The Army had been trying to arrange disposal since at least September 2025. That is where an inquiry should start.
The warning came before the emergency
On September 9, 2025, Army Contracting Command solicited bids to neutralize lead azide at Middletown. The solicitation establishes that disposal was on the Army’s agenda six months before it documented instability. The public record does not establish what the Army knew about the condition of each drum when it sought bids. The Army had flagged deterioration in a lead azide stockpile at the same plant as far back as 2004. Its published account leaves open whether that stockpile included the drums at issue today. [2]
On March 11, 2026, an inspection found that the stored lead azide had partly crystallized. In April, Army explosives personnel found crystallization in 58 of 68 drums. The federal appeals court’s account puts the material in storage at Middletown for more than two decades. Those records date the discovery and the length of storage. They leave the onset of dangerous deterioration unresolved. [3]
The Army hired a specialist contractor in late March to neutralize the stockpile and canceled the contract in May. The Army says its experts concluded that disturbing the drums to treat the material or move it posed an unacceptable risk. The EPA continued to authorize emergency storage while disposal plans took shape and issued an emergency treatment permit on November 13. The contractor’s hiring and dismissal warrant scrutiny, especially what changed between the procurement decision and the cancellation, and whether earlier action could have preserved a safer disposal option. [4]
The Army’s own sworn filing describes a further complication. By September, crystals around drum lids made opening them for the annual fluid check and refill unsafe. In November, crews preparing for the detonation removed the magazines’ heavy steel blast doors and replaced them with temporary doors. Col. Aaron Teller told the court that the original doors could not be reinstalled and that the change left the magazines more exposed to swings in outdoor temperature. The Army cited those temperature swings as a factor increasing the danger of an uncontrolled explosion. Who authorized removal of the doors before the operation had a firm date, and what contingency did that official approve? [5]
President Donald Trump ordered a pause on November 23 pending the appeal. The Eighth Circuit lifted its temporary stay later that day, clearing the way for the Army to proceed under the EPA permit. The Army’s case for acting now is serious. Its experts say the material has become too dangerous to handle and that an uncontrolled blast would carry greater risks. The sequence that left the Army with those choices deserves its own inquiry. [1, 3, 6]
Who pays after the air clears?
Families face two exposure risks. They could breathe in lead particles while the plume passes, and dust could settle on soil, windowsills and playground equipment. Exposure can continue after the air clears, particularly for young children who put dusty hands or objects in their mouths. The CDC says there is no known safe blood lead level in children. The Army’s maps are forecasts. Air, soil and surface samples will help establish what reached civilian property. [1, 7]
FEMA is supporting temporary relocation, including lodging, transportation for people who need it, and basic supplies. The EPA permit requires off-site sampling and a remediation process. Property owners can file a damage claim with the Army. Yet the public notices available on November 24 leave residents without a clear answer on reimbursement for a hotel they booked themselves, missed wages, a business closure or medical expenses. [1, 8]
At a private hazardous-waste facility, federal rules generally require financial assurance for closure and liability coverage for accidental injury or property damage. The federal government is exempt from that particular financial-assurance requirement. EPA’s emergency-permit rule also allows urgent action without an advance settlement with neighbors. That makes a written claims plan especially important. The Army can tell families which costs it will cover, what documentation it will accept and when it will decide claims while preparations continue. [9]
Kuwait and the chain of command
On March 1, an Iranian drone struck the 103rd Expeditionary Sustainment Command’s operations center at Port Shuaiba, Kuwait, killing six Army Reserve soldiers. Maj. Stephen Ramsbottom, who survived the strike, told Congress that senior military officials had dismissed warnings about inadequate protection. CBS and Associated Press reporting raised questions about the command post’s location, the protection available there and preparations to treat casualties. The Pentagon defended its precautions, and families who received briefings told CBS in November that they still had questions. The public record I reviewed leaves unresolved who received a warning specific to the port, who accepted the remaining risk and which decisions a change in command practice could have prevented. [10]
I see a command-and-control problem that warrants an independent investigation. In Kuwait, investigators should establish who chose the site, who assessed its protection, who had authority to reinforce or relocate the unit and how warnings moved up the chain. In Iowa, they should identify who owned the stockpile, who could fund and order disposal, when civilian agencies received enough information to act and who accepted the risk of further delay.
The president is accountable for the administration’s response. The defense secretary is responsible for getting answers from the chain of command and enforcing corrective action. When the Pentagon waits until people are dead overseas or families are being asked to leave home in Iowa to explain who was in charge, the White House inherits a crisis it could have pressed the department to prevent. It also gives the public little basis for judging whether the next commander will act any sooner.
How many other sites should Congress ask about?
The Army’s Joint Munitions Command oversees 17 depots, plants and storage sites that support all the armed services. Four other government-owned, contractor-operated Army ammunition plants share Iowa’s industrial designation. EPA’s open-burning and open-detonation list contains about three dozen other military facility entries in the 50 states, including separately listed annexes. These counts overlap and describe different activities. None measures how many stockpiles are deteriorating. The Army told the Associated Press that Middletown held its entire stockpile of lead azide. [11]
The Pentagon already has a national disposal problem. In January 2025, the Army recorded about 309,000 tons of ammunition and missile components in its disposal inventory. Its FY2026 budget planned to process about 29,300 tons and warned that emergency disposal becomes more hazardous as the stockpile ages. Separately, the Pentagon’s FY2025 environmental inventory showed 1,810 munitions-response sites where work had yet to reach completion, with an estimated $17.7 billion in remaining costs. That second figure reflects cleanup of past contamination and unexploded ordnance. Neither number establishes a wave of imminent evacuations. Both make the absence of a public count of deteriorating stockpiles more consequential. [12]
Five changes Congress can require
Make the Pentagon count risk as well as tonnage. Require an annual report showing how many sites hold material already showing deterioration, how many can still move it safely and how many have funded disposal plans. Congress can receive sensitive inventory details in a restricted annex. The public should be able to see aggregate risk and whether deadlines are being met.
Put one official in charge of each deteriorating stockpile. An inspection finding that material may require emergency disposal should trigger a written decision deadline, a named official with authority to secure funding and notice to civilian environmental and emergency officials where off-site effects are plausible. Preserve the commander’s ability to act immediately in an imminent emergency. Require a public after-action review with dates and decisions.
Give local officials a role before the disposal decision. Middletown already had a Restoration Advisory Board for cleanup. Bring that board together with the county emergency planning committee, EPA, state health and environmental officials, schools, first responders, and affected neighboring or tribal governments. Have them review and exercise the off-site plan annually, including who can issue an alert, how residents will be moved and who determines when they can return. [13]
Let civilian regulators verify exposure and cleanup. EPA and the state should agree on sampling locations in advance, commission independent checks on a share of the samples and publish neighborhood-level results. An airborne all-clear should answer when residents can return. The cleanup findings should tell them whether their yard, school or business needs remediation.
Publish a claims plan before asking people to leave. Give residents one point of contact and written terms for transportation, lodging and property damage. Spell out how lost wages, business interruptions, medical expenses and privately incurred cleanup costs will be handled. Where current authority is insufficient, ask Congress for explicit authority and funding. The plan should state what records residents need and how to appeal a denial.
The question for the Pentagon is straightforward. How many stockpiles are deteriorating today, who has the authority and funding to dispose of each one, and when will the people living next door be told? Middletown shows what happens when those questions wait until the week of the blast.
Endnotes
U.S. Army, November 24 public safety advisory and relocation arrangements.
Army Contracting Command, September 2025 lead azide neutralization solicitation. U.S. Army, 2014 account of the earlier Middletown stockpile concern.
Eighth Circuit, Iowa Environmental Council v. EPA, November 23 order. U.S. Army, November 24 advisory, including the March 11 inspection.
Iowa Public Radio, The neutralization contract and its cancellation. EPA, November emergency treatment permit notice.
Col. Aaron C. Teller, sworn declaration filed November 21, paragraphs 9–14 and 26–29.
Reuters, Trump’s pause, the court ruling and the Army’s decision to proceed.
Iowa Poison Control Center, lead dust exposure and health guidance. CDC, childhood lead exposure and health effects.
EPA, emergency permit, including sampling and remediation requirements. KWQC via KCRG, Middletown property damage claims. Army Judge Advocate General’s Corps, filing a tort claim.
EPA, hazardous-waste financial assurance rules. 40 CFR § 264.140, including the government exemption. 40 CFR § 270.61, emergency permits.
Protected disclosure to Congress on Port Shuaiba. Associated Press, soldiers and families press Army leadership. CBS News, Pentagon response and reporting on basing decisions, and Gold Star families’ account of the November briefings.
U.S. Army, Joint Munitions Command’s network. GAO, Army Ammunition, including the five government-owned plants. EPA, current open-burning and open-detonation facility list. Associated Press, November 24 reporting on the lead azide stockpile.
U.S. Army, FY2026 ammunition budget justification, Conventional Munitions Demilitarization. Defense Environmental Restoration Program, FY2025 inventory and cost estimates.
EPA, Iowa Army Ammunition Plant Superfund profile and existing Restoration Advisory Board. U.S. Army, October 15 open house. EPA, local and tribal emergency planning committees.




Comments